Construction already finished on the facility that pictures are posted for early in this thread. We leased space at that data center from the data center owner, however, we were forced to move about 50 miles away to Quincy, WA this summer when the owner was not able meet the cooling demands that miners require in the Washington summer.
Will this new hosting center at Quincy be permanent from now on? Or, are you willing to move back to the former one after the owner meets with the cooling demands?
The Quincy site is currently fully operational
Damn you!

Please shoot me a PM ASAP, mentioning the full shipping address of your center. I'll be delivering 2 of my bad boys there.

we are offering the rate of $55/kw/mo (7.5 cents/kwh) to both small and large customers.
Well, I can smell some profitability with your current rate.

(Calculated on
Coinwarz)

So, let's get started!