What are the current plans for chip development?
ActiveMining is in the process of gathering necessary funds for paying NRE costs on its 28nm chip. We hope these funds to be gathered soon, so that chip production can start as soon as possible. Estimated dates after NRE payment are:
  • Chip samples delivered in 9 weeks;
  • Low-volume chip production starting in 12 weeks, using an e-beam process;
  • Normal volume chip production starting in 16-18 weeks.

The above is from Ken on the first page of this thread.

Ken has mentioned the bitcoins have have already been converted to fiat, and therefore I presume the NRE has been paid.

So ....... 9 weeks after NRE is paid, we should get news about chip samples being in hand.

Anyone hazard a guess as to when the NRE was paid, and so 9 weeks is when??