Board Hardware
Re: Incoming Avalon News 8/9/2013
by
itod
on 31/08/2013, 21:34:45 UTC
I think half a week late is pretty good, if chips arrives on wednesday and we send them out no?

How can you be so sleazy? Chips are not half a week late, they are 10 1/2 weeks late. You've broken your no-bullshit agreement, refund everybody who are fucked by your incompetence and keep your worthless chips to yourself. Or you can sell them on Alibaba, you seem to have mastered that distribution channel.

they are ordered on june 15th, not due june 15th... the lead time is 10 weeks, so yes, 1/2 weeks late is correct.

If you ship them on wednesday, there's no chance anyone can receive them before monday, September 9th. That's more than 12 weeks:
http://www.timeanddate.com/date/durationresult.html?d1=15&m1=06&y1=2013&d2=09&m2=09&y2=2013
I have nothing else to say but you don't have enough ethics not only to fulfill past promises but also what you've promised day before yesterday.