That's LukeJr. He gets everything first. What about the rest of us? :/
Josh,
The email they sent clearly states nothing will be happening till they test the new stuff..
quoted:
Dear Batch 1 Customers,
Although HashFast has enough Golden Nonce ASICS for all Batch 1 orders, our initial modules (Rev 0) had reliability issues due to the PCB layout (Printed Circuit Boards).We have now received 2nd rev PCBs, and they are currently being assembled and will then be tested.
Despite these challenges we did begin shipping our very first Batch 1 orders today. These units were hand-built, tuned and tested. We have not yet started bulk production due to continued debugging efforts on the latest PCB revision.
We had hoped to resolve reliability issues sooner so that we could begin bulk production and be on track to ship Batch 1 customer orders on December 31. However, issues have not been adequately resolved, and therefore we are unable to ship the remaining outstanding orders by December 31st.