Not to be dismissive, but the chances of that happening are almost non-existent. You're talking about a 2MW datacenter there, probably 3MW with cooling.

Dismissive is one word, completely ignorant might be another term that applies.

A quick search found this:

location - Kansas MO
power - 9MegaWatts of power capacity over 4 transformers
space - 11,000 square foot of space
rental - $4,680 per month

Unless I'm missing something opening a Bitcoin date centre for 2, 3 or 10 MW is as difficult as taking out a lease and installing your miners.

http://www.cityfeet.com/cont/ForLease/LN18343927/1800-Reynolds-Avenue-Kansas-City-MO-64120

Edit - it even has 120 parking spaces and a 15 Ton bridge crane. What more could you need?