Total Hashrate now is ~2100Th and ken wants to deploy 1300Th in May that will consume a staggering 1700 MW? Now this is one hell of optimistic projection.

How will he get/cool 1700MW? How many chips are needed for 1300Th? And only 1.3 mil $ for more than 50% of current network? How come nobody else noticed these points?

Total hashrate now is 16PH/s - ken is looking to deploy 1.3PH/s and the total projected network hashrate at that time is 96PH/s

Also, ken only needs 1.7MW

Your maths sucks dude.