Is a batch 3 likely ?

Batch 2 progress...Huh
Batch 2 is progressing nicely, all the boards are built and are on their way through testing now. We don't expect to be late at all with starting shipping early next week.

On thursday you said that you expected to be opening batch two back up once you had a good idea of yields and such.  Do you still plan on doing this?  If not,  let me (us) know so we can stop repeatedly checking the site... really hoping I can get some boards in this batch =)