Page 20 of your ICO
Projected Timeline
The size of the Giga Watt facility depends on the amount of available funds. The Giga Watt
project has sufficient commitments for land and electricity to build additional capacities to
fulfil its obligations under this Token Launch.
Projected Token Launch Timeline
- May 19 June 2, 2017: pre-sale
- June 2 July 31, 2017: Token Launch book building
- August 7, 2017: First batch of tokens (5,400,000 WTT) issued to participants; if the cap is
reached earlier, the first batch of WTT tokens may be issued ahead of the schedule to provide
access to the facilities built by the time of the issue (at Cryptonomos' discretion).
New batches of tokens will be issued in step with the construction of new facilities.22 To ensure
the advantage for the Token Launch participants, no listing will be placed on third party
exchanges until all WTT tokens sold through the Token Launch are distributed.
Projected Construction Timeline
3 units, 2.25 MW are available right now
- July 15, 2017: 1 Giga Pod completed, 0.75 MW
- August 1, 2017: 2 Giga Pods completed, 2.4MW
- August 15, 2017: Expansion of the unit, 0.9 MW
- September 1, 2017: 3 Giga Pods completed, 4.5 MW
- September 15, 2017: 9 Giga Pods completed, 15 MW
22 Additional WTT tokens may be sold to the public in the future as the facility capacity is increased through
build outs.
21
134834324.1
- October 1, 2017: 3 Giga Pods completed, 4.5 MW
- November 15, 2017: 3 Giga Pods completed, 4.2 MW
WTT tokens may be sold to the public in the future as the facility capacity is increased through
build outs.
On top of that tokens willl not be available untill October 1st on ANY EXCHANGE..
GG speculation..